Construction updates for spec homes
2008-Apr-29
Spec #1
- 100% Decks & railings
- 100% Cabinets, vanities & mirrors
- 100% Mechanical equipment
- 97% Plumbing fixtures
- 95% Electrical finish
- 100% Granite tops
- 100% Complete to exterior feature wall
- 100% Interior paint
- 100% Septic field

Spec #2
- 50% Rough render
- 80% Concrete hurricane ties
- 100% Block work
- 100% Framing roof system
- 100% Sewer tanks

Spec #3
- 100% A.C finish
- 100% Exterior doors
- 100% Tape & texture
- 100% Soffit finish
- 100% Wall & counter tile
- 100% Counter tops
- 100% Cabinets & vanities
- 100% Mechanical equipment
- 100% Sewer system
- 90% Electrical finish
- 90% Plumbing finish

Spec #4
- 90% Concrete placing for hurricane ties
- 100% Roof system
- 70% Rough rendering