Construction updates for spec homes
2008-Apr-29

Spec #1

  • 100% Decks & railings
  • 100% Cabinets, vanities & mirrors
  • 100% Mechanical equipment
  • 97% Plumbing fixtures
  • 95% Electrical finish
  • 100% Granite tops
  • 100% Complete to exterior feature wall
  • 100% Interior paint
  • 100% Septic field

Spec #2

  • 50% Rough render
  • 80% Concrete hurricane ties
  • 100% Block work
  • 100% Framing roof system
  • 100% Sewer tanks

Spec #3

  • 100% A.C finish
  • 100% Exterior doors
  • 100% Tape & texture
  • 100% Soffit finish
  • 100% Wall & counter tile
  • 100% Counter tops
  • 100% Cabinets & vanities
  • 100% Mechanical equipment
  • 100% Sewer system
  • 90% Electrical finish
  • 90% Plumbing finish

Spec #4

  • 90% Concrete placing for hurricane ties
  • 100% Roof system
  • 70% Rough rendering