May Updates for Spec Home Construction
2008-May-30
*Please Note: Spec home 1 has been delayed due to the late arrival of the Jacuzzi bath tubs. These tubs should be arriving in the first week of June.
Spec #1
- 100% Decks & railings
- 100% Cabinets, vanities & mirrors
- 100% Mechanical equipment
- 97% Plumbing fixtures
- 95% Electrical finish
- 100% Granite tops
- 100% Complete to exterior feature wall
- 100% Interior paint
- 100% Septic field
- 100% External Staircases
- 100% Door & window casings
- 95% Internal staircase
Spec #2
- 50% Rough render
- 100% Concrete hurricane ties
- 100% Block work
- 100% Framing roof system
- 100% Roof waterproofing
- 100% Sewer tanks
Spec #3
- 100% AC finish
- 100% Exterior doors
- 100% Tape & texture
- 100% Soffit finish
- 100% Wall & counter tile
- 100% Counter tops
- 100% Cabinets & vanities
- 100% Mechanical equipment
- 100% Sewer system
- 90% Electrical finish
- 90% Plumbing finish
Spec #4
- 90% Rough rendering
- 100% Concrete placing for hurricane ties
- 100% Roof system
- 100% Roof waterproofing membrane
- 100% Roof tiles