May Updates for Spec Home Construction
2008-May-30

*Please Note: Spec home 1 has been delayed due to the late arrival of the Jacuzzi bath tubs. These tubs should be arriving in the first week of June.

Spec #1

  • 100% Decks & railings
  • 100% Cabinets, vanities & mirrors
  • 100% Mechanical equipment
  • 97% Plumbing fixtures
  • 95% Electrical finish
  • 100% Granite tops
  • 100% Complete to exterior feature wall
  • 100% Interior paint
  • 100% Septic field
  • 100% External Staircases
  • 100% Door & window casings
  • 95% Internal staircase
1

Spec #2

  • 50% Rough render
  • 100% Concrete hurricane ties
  • 100% Block work
  • 100% Framing roof system
  • 100% Roof waterproofing
  • 100% Sewer tanks
2

Spec #3

  • 100% AC finish
  • 100% Exterior doors
  • 100% Tape & texture
  • 100% Soffit finish
  • 100% Wall & counter tile
  • 100% Counter tops
  • 100% Cabinets & vanities
  • 100% Mechanical equipment
  • 100% Sewer system
  • 90% Electrical finish
  • 90% Plumbing finish
3

Spec #4

  • 90% Rough rendering
  • 100% Concrete placing for hurricane ties
  • 100% Roof system
  • 100% Roof waterproofing membrane
  • 100% Roof tiles
4