May Updates for Triplexes
2008-May-30

*Please Note: Spec home 1 has been delayed due to the late arrival of the Jacuzzi bath tubs. These tubs should be arriving in the first week of June.

Triplex #1

  • 100% Rear stairs
  • 100% Complete roof system
  • 95% Plumbing 1st level
  • 100% Hurricane ties
  • 100% Front stairs
  • 100% Electrical rough in 1st floor interior
  • 100% Electrical exterior wall 2nd level
  • 100% Plumbing rough in 2nd level
  • 100% Window installation
  • 100% Roof waterproofing membrane
  • 100% Roof Decra Tiles
1

Triplex #2

  • 100% Roof system
  • 90% Plumbing 1st level
  • 60% Electrical main floor
  • 100% Front stairs
  • 100% Rear stairs
  • 100% Ring beam
  • 100% Concrete for hurricane ties
  • 100% 1st floor framing & strapping
  • 100% Roof waterproofing membrane
2

Triplex #6

  • 100% Installation of 2nd floor double T’s
  • 100% Concrete to columns for 2nd floor
3

Triplex #7

  • 100% Ring beam
  • 100% Block work to 2nd level
  • 100% Strapping & framing to 1st level
  • 100% Strapping & framing to 2nd level
  • 95% Plumbing rough in 1st level
  • 65% Electrical rough in 1st level
  • 95% Plumbing rough in 2nd level
  • 65% Electrical rough in 2nd level
  • 100% Front stairs
  • 100% Rear stairs
  • 100% Ring beam
  • 100% Window installation
  • 100% Concrete for hurricane ties
  • 100% Roof waterproofing membrane
  • 80% Roof tiles