May Updates for Triplexes
2008-May-30
*Please Note: Spec home 1 has been delayed due to the late arrival of the Jacuzzi bath tubs. These tubs should be arriving in the first week of June.
Triplex #1
- 100% Rear stairs
- 100% Complete roof system
- 95% Plumbing 1st level
- 100% Hurricane ties
- 100% Front stairs
- 100% Electrical rough in 1st floor interior
- 100% Electrical exterior wall 2nd level
- 100% Plumbing rough in 2nd level
- 100% Window installation
- 100% Roof waterproofing membrane
- 100% Roof Decra Tiles
Triplex #2
- 100% Roof system
- 90% Plumbing 1st level
- 60% Electrical main floor
- 100% Front stairs
- 100% Rear stairs
- 100% Ring beam
- 100% Concrete for hurricane ties
- 100% 1st floor framing & strapping
- 100% Roof waterproofing membrane
Triplex #6
- 100% Installation of 2nd floor double T’s
- 100% Concrete to columns for 2nd floor
Triplex #7
- 100% Ring beam
- 100% Block work to 2nd level
- 100% Strapping & framing to 1st level
- 100% Strapping & framing to 2nd level
- 95% Plumbing rough in 1st level
- 65% Electrical rough in 1st level
- 95% Plumbing rough in 2nd level
- 65% Electrical rough in 2nd level
- 100% Front stairs
- 100% Rear stairs
- 100% Ring beam
- 100% Window installation
- 100% Concrete for hurricane ties
- 100% Roof waterproofing membrane
- 80% Roof tiles