Jun 2008 Construction Updates
2008-Jun-29

Spec #1

  • 100% Decks & railings
  • 100% Cabinets, vanities & mirrors
  • 100% Mechanical equipment
  • 100% Plumbing fixtures
  • 99% Electrical finish
  • 100% Granite Tops
  • 100% Complete to exterior feature wall
  • 100% Interior paint
  • 100% Septic Field
  • 100% External Staircases
  • 100% Door and window casings
  • 98% Internal staircase
1 1.1 1.2 1.3

Spec #2

  • 50% Rough render
  • 100% Concrete hurricane ties
  • 100% Block work
  • 100% Framing roof system
  • 100% Sewer tanks
  • 30% Roof tiles
2

Spec #3

  • 100% AC finish
  • 100% Exterior doors
  • 100% Tape & texture
  • 100% Soffit finish
  • 100% Wall & counter tile
  • 100% Counter tops
  • 100% Cabinets & vanities
  • 100% Mechanical equipment
  • 100% Sewer system
  • 98% Electrical finish
  • 98% Plumbing finish
3

Spec #4

  • 100% Rough rendering
  • 100% Concrete placing for hurricane ties
  • 100% Roof system
  • 100% Roof waterproofing membrane
  • 100% Roof tiles
  • 100% Windows
  • 100% External doors
4

Triplex #1

  • 100% Rear stairs
  • 100% Complete roof system
  • 95% Plumbing 1st level
  • 100% Hurricane ties
  • 100% Front stairs
  • 100% Electrical rough in 1st floor interior
  • 100% Electrical exterior wall 2nd level100% Plumbing rough in 2nd level
  • 100% Window installation
  • 100% Roof waterproofing membrane
  • 100% Roof Decra Tiles
1

Triplex #2

  • 100% Roof system
  • 90% Plumbing 1st level
  • 60% Electrical main floor
  • 100% Front stairs
  • 100% Rear stairs
  • 100% Ring beam
  • 100% Concrete for hurricane ties
  • 100% 1st floor framing & strapping
  • 100% 2nd floor framing & strapping
  • 100% Roof waterproofing membrane
  • 100% Windows
2

Triplex #6

  • 100% Installation of 2nd floor double T’s
  • 100% Concrete to columns for 2nd floor
  • 100% Blockwork to 2nd Floor
  • 100% Formwork to Ring Beam
  • 100% Reinforcing to Ring Beam
  • 50% Reinforcing to Front Staircase
3

Triplex #7

  • 100% Ring beam
  • 100% Block work to 2nd level
  • 100% Strapping & framing to 1st level
  • 100% Strapping & framing to 2nd level
  • 100% Plumbing rough in 1st level
  • 100% Electrical rough in 1st level
  • 95% Plumbing rough in 2nd level
  • 95% Electrical rough in 2nd level
  • 100% Front stairs
  • 100% Rear stairs
  • 100% Ring beam
  • 100% Window installation
  • 25% Acrylic to outside walls
  • 100% Concrete for hurricane ties
  • 100% Roof waterproofing membrane
  • 100% Roof tiles
  • 50% A.C. Installation
4 5

Sixplex #3

  • 100% Pile installation
  • 100% Ground beams
  • 100% Stub columns to ground floor beams
  • 100% Formwork to ground floor beams
  • 100% Concrete to ground floor ring beam

1

Sixplex #4

  • 100% Pile installation
  • 100% Cut pile tops
  • 100% Formwork to grade beams
2

Sixplex #5

  • 100% Pile installation
  • 100% Cutting of piles
  • 100% Grade foundations
  • 100% Grade level columns
  • 100% Formwork to ground floor beams
  • 100% Concrete to ground floor ring beam

3

PLANS FOR NEXT PERIOD

SPEC HOMES

  • Focus on completing units 1 & 3
  • Units 2 & 4:
    • Complete roofs including ice & water protection & tiles.
    • Complete rough rendering
    • Install windows and seal unit until we can carry on with construction.

PHASE 3 LOOP 1

TRI-PLEX’S

  • Focus on TP 7 with roof up to water & ice stage as the supplier of the Decra roof tiles is due to arrive on site on 19th May to train our personnel to install the roofing tiles.
  • Metal studs to TP # 1,# 2 and # 7 and rough render all units
  • Plumbing and electrical installation

6-PLEX

  • Excavate for grade beams and cast concrete
  • Start with grade beam columns
«Back to all News Items
 