Jun 2008 Construction Updates
2008-Jun-29
Spec #1
- 100% Decks & railings
- 100% Cabinets, vanities & mirrors
- 100% Mechanical equipment
- 100% Plumbing fixtures
- 99% Electrical finish
- 100% Granite Tops
- 100% Complete to exterior feature wall
- 100% Interior paint
- 100% Septic Field
- 100% External Staircases
- 100% Door and window casings
- 98% Internal staircase
Spec #2
- 50% Rough render
- 100% Concrete hurricane ties
- 100% Block work
- 100% Framing roof system
- 100% Sewer tanks
- 30% Roof tiles
Spec #3
- 100% AC finish
- 100% Exterior doors
- 100% Tape & texture
- 100% Soffit finish
- 100% Wall & counter tile
- 100% Counter tops
- 100% Cabinets & vanities
- 100% Mechanical equipment
- 100% Sewer system
- 98% Electrical finish
- 98% Plumbing finish
Spec #4
- 100% Rough rendering
- 100% Concrete placing for hurricane ties
- 100% Roof system
- 100% Roof waterproofing membrane
- 100% Roof tiles
- 100% Windows
- 100% External doors
Triplex #1
- 100% Rear stairs
- 100% Complete roof system
- 95% Plumbing 1st level
- 100% Hurricane ties
- 100% Front stairs
- 100% Electrical rough in 1st floor interior
- 100% Electrical exterior wall 2nd level100% Plumbing rough in 2nd level
- 100% Window installation
- 100% Roof waterproofing membrane
- 100% Roof Decra Tiles
Triplex #2
- 100% Roof system
- 90% Plumbing 1st level
- 60% Electrical main floor
- 100% Front stairs
- 100% Rear stairs
- 100% Ring beam
- 100% Concrete for hurricane ties
- 100% 1st floor framing & strapping
- 100% 2nd floor framing & strapping
- 100% Roof waterproofing membrane
- 100% Windows
Triplex #6
- 100% Installation of 2nd floor double T’s
- 100% Concrete to columns for 2nd floor
- 100% Blockwork to 2nd Floor
- 100% Formwork to Ring Beam
- 100% Reinforcing to Ring Beam
- 50% Reinforcing to Front Staircase
Triplex #7
- 100% Ring beam
- 100% Block work to 2nd level
- 100% Strapping & framing to 1st level
- 100% Strapping & framing to 2nd level
- 100% Plumbing rough in 1st level
- 100% Electrical rough in 1st level
- 95% Plumbing rough in 2nd level
- 95% Electrical rough in 2nd level
- 100% Front stairs
- 100% Rear stairs
- 100% Ring beam
- 100% Window installation
- 25% Acrylic to outside walls
- 100% Concrete for hurricane ties
- 100% Roof waterproofing membrane
- 100% Roof tiles
- 50% A.C. Installation
Sixplex #3
- 100% Pile installation
- 100% Ground beams
- 100% Stub columns to ground floor beams
- 100% Formwork to ground floor beams
- 100% Concrete to ground floor ring beam
Sixplex #4
- 100% Pile installation
- 100% Cut pile tops
- 100% Formwork to grade beams
Sixplex #5
- 100% Pile installation
- 100% Cutting of piles
- 100% Grade foundations
- 100% Grade level columns
- 100% Formwork to ground floor beams
- 100% Concrete to ground floor ring beam

PLANS FOR NEXT PERIOD
SPEC HOMES
- Focus on completing units 1 & 3
- Units 2 & 4:
- Complete roofs including ice & water protection & tiles.
- Complete rough rendering
- Install windows and seal unit until we can carry on with construction.
PHASE 3 LOOP 1
TRI-PLEX’S
- Focus on TP 7 with roof up to water & ice stage as the supplier of the Decra roof tiles is due to arrive on site on 19th May to train our personnel to install the roofing tiles.
- Metal studs to TP # 1,# 2 and # 7 and rough render all units
- Plumbing and electrical installation
6-PLEX
- Excavate for grade beams and cast concrete
- Start with grade beam columns